CLIENT:
JP Elektroprivreda Srbije (Electrical Power Industry of Serbia)/TPP Nikola Tesla Ltd.

PROJECT STATUS:
Completed

PROJECT VALUE:
7,300,000 EUR

DESCRIPTION OF THE PROJECT:
Turnkey

PROGRAM OF WORKS

  • Year of completion / handover to the Client – 2007.
  • End of Contract / end of guarantee period – 2008.

 

BASIC PROJECT FEATURES

The scope of the works and services provides concentrations of fly ash particles in the flue gas at the outlet of the electrostatic precipitator less than 50mg / Nm3.

Basic Unit parameters: power 308.5 MW, type of coal – lignite

 

DESCRIPTION OF WORKS

Reconstruction of the electrostatic precipitator includes disassembling of the old equipment and ash handling system, design, procurement, installation, testing and commissioning of the new equipment with related civil, mechanical and electrical works

 

ENVIRONMENTAL PROTECTION PROJECT

The realization of the project made it possible to increase the efficiency of the operation of the ESP Unit.

 

The project implementation resulted in a multiple reduction of the outlet flue gas dust concentration and increasing efficiency of plant operation, while meeting regulatory environmental requirements associated with maximum permissible dust emission levels less than 50 mg / Nm3.